We recommend that the Director of the Office of Block Grant Assistance require the Texas GLO to provide its plan to ensure that processes are in place to assist those participants transitioning from the City’s programs to the Texas GLO’s programs.
Publication Report
2022-FW-1001 | January 04, 2022
The City of Houston, Houston, TX, Faced Challenges in Administering Its Hurricane Harvey Program and Risked Losing Its Funding
We audited the City of Houston’s Hurricane Harvey Community Development Block Grant Disaster Recovery (CDBG-DR) program. We initiated this audit as part of our commitment to helping the U.S. Department of Housing and Urban Development (HUD) address… moreRelated Recommendations
Community Planning and Development
We recommend that the Director of the Office of Block Grant Assistance require the Texas GLO to include milestones and appropriate consequences for not meeting those milestones in future subrecipient agreements to ensure that expenditure deadlines remain on track. Implementing this recommendation could assist the Texas GLO in avoiding possible future litigation based on the lack of required benchmarks in its contracts.
With HUD’s approval of action plan amendment 8, we recommend that the Director of the Office of Block Grant Assistance require the Texas GLO to provide its plan to continuously monitor the City’s pace and performance in its remaining Hurricane Harvey CDBG-DR program and take appropriate action to ensure that program goals are met. The plan should include a process for repurposing additional grant funds, if necessary, to avoid potential recapture due to the City’s inability to meet the expenditure deadline established under its subrecipient agreement with the Texas GLO and to allow the Texas GLO to meet the expenditure deadline for its grant award.
With HUD’s approval of action plan amendment 8, we recommend that the Director of the Office of Block Grant Assistance require the Texas GLO to set performance and financial milestones, including approval of the City’s projects and obligation and expenditure of funds, for all programs and activities funded under the City’s subrecipient agreement through the remainder of the contract and deadlines for the City to achieve those milestones. This requirement would include the Texas GLO’s (1) providing its plan to continually assess whether the City is meeting the established milestones within the prescribed period; (2) taking appropriate action as outlined in the subrecipient agreement for any missed deadlines; and (3) if necessary, determining whether programs need to be combined or eliminated from the subrecipient agreement.
With HUD’s approval of action plan amendment 8, we recommend that the Director of the Office of Block Grant Assistance require the Texas GLO to provide its plan to ensure that the City will comply with the Texas GLO’s program guidelines and required onsite technical assistance and supportive services. This plan would include (1) precise instructions and deadlines for submitting or resubmitting program and implementation guidelines, (2) terms for settling technical assistance and supportive services disagreements, and (3) appropriate consequences for noncompliance with the requirements the Texas GLO imposes.