The OIG has determined that the contents of this recommendation would not be appropriate for public disclosure and has therefore limited its distribution to selected officials.
2018-OE-0003 | October 31, 2018
HUD Fiscal Year 2018 Federal Information Security Modernization Act of 2014 (FISMA) Evaluation Report
Chief Information Officer
- Status2018-OE-0003-25OpenClosedSensitiveSensitive
Sensitive information refers to information that could have a damaging import if released to the public and, therefore, must be restricted from public disclosure.
Closed on May 16, 2024 - Status2018-OE-0003-26OpenClosedSensitiveSensitive
Sensitive information refers to information that could have a damaging import if released to the public and, therefore, must be restricted from public disclosure.
Closed on December 01, 2020The OIG has determined that the contents of this recommendation would not be appropriate for public disclosure and has therefore limited its distribution to selected officials.
- Status2018-OE-0003-27OpenClosedSensitiveSensitive
Sensitive information refers to information that could have a damaging import if released to the public and, therefore, must be restricted from public disclosure.
Closed on February 02, 2022The OIG has determined that the contents of this recommendation would not be appropriate for public disclosure and has therefore limited its distribution to selected officials.
- Status2018-OE-0003-28OpenClosedSensitiveSensitive
Sensitive information refers to information that could have a damaging import if released to the public and, therefore, must be restricted from public disclosure.
Closed on November 19, 2020The OIG has determined that the contents of this recommendation would not be appropriate for public disclosure and has therefore limited its distribution to selected officials.
- Status2018-OE-0003-29OpenClosedSensitiveSensitive
Sensitive information refers to information that could have a damaging import if released to the public and, therefore, must be restricted from public disclosure.
Closed on November 19, 2020The OIG has determined that the contents of this recommendation would not be appropriate for public disclosure and has therefore limited its distribution to selected officials.
- Status2018-OE-0003-30OpenClosedSensitiveSensitive
Sensitive information refers to information that could have a damaging import if released to the public and, therefore, must be restricted from public disclosure.
Closed on July 15, 2025The OIG has determined that the contents of this recommendation would not be appropriate for public disclosure and has therefore limited its distribution to selected officials.
2018-CF-0802 | September 27, 2018
HUD Failed To Enforce the Terms of a Settlement Agreement With Fifth Third Bank Because It Did Not Record Indemnified Loans in Its Tracking System
Housing
- Status2018-CF-0802-001-AOpenClosed$311,699Questioned Costs
Recommendations with questioned costs identify costs: (A) resulting from an alleged violation of a law, regulation, contract, grant, or other document or agreement governing the use of Federal funds; (B) that are not supported by adequate documentation (also known as an unsupported cost); or (C) that appear unnecessary or unreasonable.
Closed on June 09, 2020Require FTB to reimburse HUD $311,699 for 2 loans for which HUD incurred losses when it sold the properties and 15 loans for which FHA insurance had been terminated and HUD had paid loss mitigation claims to FTB.
- Status2018-CF-0802-001-BOpenClosed$47,433,895Funds Put to Better Use
Recommendations that funds be put to better use estimate funds that could be used more efficiently. For example, recommendations that funds be put to better use could result in reductions in spending, deobligation of funds, or avoidance of unnecessary spending.
Closed on June 09, 2020Record in FHA Connection the remaining indemnified loans, avoiding $47,433,895 in estimated losses. The estimated loss is based on the loss severity rate of 46 percent of the total unpaid principal balance of $103,117,164.
- Status2018-CF-0802-001-COpenClosedClosed on March 11, 2020
Develop and implement controls to ensure that indemnification agreements that result from U.S. Department of Justice settlements have been properly recorded in FHA Connection.
- Status2018-CF-0802-001-DOpenClosedClosed on June 01, 2020
Take appropriate administrative action against FTB for violations of the settlement agreement.
2018-CH-1009 | September 27, 2018
The Owner and Management Agent for Rainbow Terrace Apartments, Cleveland, OH, Did Not Always Operate the Project in Accordance With the Regulatory Agreement and HUD’s Requirements
Housing
- Status2018-CH-1009-001-AOpenClosed$2,232,004Questioned Costs
Recommendations with questioned costs identify costs: (A) resulting from an alleged violation of a law, regulation, contract, grant, or other document or agreement governing the use of Federal funds; (B) that are not supported by adequate documentation (also known as an unsupported cost); or (C) that appear unnecessary or unreasonable.
Closed on September 21, 2020Support the reasonableness of or reimburse the project $2,232,004 ($1,719,736 $484,615 $27,653) from nonproject funds for the project funds disbursed without sufficient procurement or contract documentation.
- Status2018-CH-1009-001-BOpenClosed$7,091Questioned Costs
Recommendations with questioned costs identify costs: (A) resulting from an alleged violation of a law, regulation, contract, grant, or other document or agreement governing the use of Federal funds; (B) that are not supported by adequate documentation (also known as an unsupported cost); or (C) that appear unnecessary or unreasonable.
Closed on January 22, 2020Support or reimburse the project from nonproject funds $7,091, as appropriate, for the project funds disbursed without sufficient supporting documentation.
- Status2018-CH-1009-001-COpenClosed$46,024Questioned Costs
Recommendations with questioned costs identify costs: (A) resulting from an alleged violation of a law, regulation, contract, grant, or other document or agreement governing the use of Federal funds; (B) that are not supported by adequate documentation (also known as an unsupported cost); or (C) that appear unnecessary or unreasonable.
Closed on February 20, 2020Reimburse the project from nonproject funds $46,024 for the project funds that were not used for reasonable operating expenses or necessary repairs of the project.
- Status2018-CH-1009-001-DOpenClosed$39,690Questioned Costs
Recommendations with questioned costs identify costs: (A) resulting from an alleged violation of a law, regulation, contract, grant, or other document or agreement governing the use of Federal funds; (B) that are not supported by adequate documentation (also known as an unsupported cost); or (C) that appear unnecessary or unreasonable.
Closed on February 12, 2020Support or reimburse the project from nonproject funds $39,690, as appropriate, for the project funds disbursed without sufficient documentation supporting that the invoices were not for duplicate work.
- Status2018-CH-1009-001-EOpenClosedClosed on January 17, 2020
Implement adequate procedures and controls to ensure that project funds are used for only reasonable operating expenses or necessary repairs when the project is in a non-surplus-cash position.
- Status2018-CH-1009-001-FOpenClosed$95,174Questioned Costs
Recommendations with questioned costs identify costs: (A) resulting from an alleged violation of a law, regulation, contract, grant, or other document or agreement governing the use of Federal funds; (B) that are not supported by adequate documentation (also known as an unsupported cost); or (C) that appear unnecessary or unreasonable.
Closed on January 09, 2020Reimburse the project $95,174 from nonproject funds for management fees in excess of the maximum yield.
- Status2018-CH-1009-001-GOpenClosed$70,632Questioned Costs
Recommendations with questioned costs identify costs: (A) resulting from an alleged violation of a law, regulation, contract, grant, or other document or agreement governing the use of Federal funds; (B) that are not supported by adequate documentation (also known as an unsupported cost); or (C) that appear unnecessary or unreasonable.
Closed on January 23, 2020Support or reimburse the project $70,632 from nonproject funds, as appropriate, for the project funds disbursed to Vesta Corporation for bookkeeping fees without documentation showing that the bookkeeping fees charged were reasonable.
- Status2018-CH-1009-001-HOpenClosedClosed on January 07, 2020
Implement adequate procedures and controls, including but not limited to ensuring that the project receives HUD’s communications to ensure that its management and bookkeeping fees comply with HUD’s requirements.
- Status2018-CH-1009-001-IOpenClosedClosed on December 16, 2019
Implement adequate procedures and controls to ensure that its bookkeeping fees are based on actual costs.
- Status2018-CH-1009-001-JOpenClosedClosed on January 08, 2020
Use the project’s security deposits bank account to deposit and disburse security deposits.