Require the Housing Authority of Brevard County to repay $1,520 in ineligible escrow funds to HUD from non-Federal funds for the program participant that exceeded allowable contract terms of the FSS program.
2018-PH-0002 | September 09, 2018
HUD Did Not Provide Adequate Oversight of Its Family Self-Sufficiency Program
Public and Indian Housing
- Status2018-PH-0002-001-BOpenClosed$1,520Questioned Costs
Recommendations with questioned costs identify costs: (A) resulting from an alleged violation of a law, regulation, contract, grant, or other document or agreement governing the use of Federal funds; (B) that are not supported by adequate documentation (also known as an unsupported cost); or (C) that appear unnecessary or unreasonable.
Closed on July 17, 2019 - Status2018-PH-0002-001-COpenClosedClosed on February 13, 2020
Monitor the grantees’ efforts to improve the accuracy and completeness of the PIC program data to ensure that program outcomes reported to Congress are accurately supported.
- Status2018-PH-0002-001-DOpenClosedClosed on February 27, 2020
Develop and implement a plan to monitor grantee FSS programs, including to ensure that escrow accounts are calculated correctly.
- Status2018-PH-0002-001-EOpenClosedClosed on May 16, 2019
Develop and implement policies and procedures to ensure that documentation is maintained by grantees to support program participants’ contractual agreements.
2018-FW-0003 | August 30, 2018
REAC Could Improve Its Inspections Processes and Controls
Public and Indian Housing
- Status2018-FW-0003-001-AOpenClosedClosed on November 07, 2019
We recommend that the Deputy Assistant Secretary for REAC require REAC to develop and implement written policies and procedures requiring REAC to (1) select a sample of inspector candidates, (2) require the sampled inspector candidates to provide written documentation supporting their minimum qualifications, (3) verify the written documentation provided by the inspector candidates, and (4) document the completion of the verification and method(s) used to verify the documentation.
- Status2018-FW-0003-001-BOpenClosedClosed on November 07, 2019
We recommend that the Deputy Assistant Secretary for REAC require REAC to ensure that the nine contract inspectors, who did not meet the minimum requirements to begin the training, receive specialized training in residential or commercial building for electrical; heating, ventilation, and air conditioning; masonry; plumbing; and carpentry, as applicable.
- Status2018-FW-0003-001-COpenClosedClosed on November 07, 2019
We recommend that the Deputy Assistant Secretary for REAC require REAC to develop, use, and document an electronic checklist for each contract inspector’s file to ensure that inspectors (1) obtain and maintain the required insurance, and (2) have approved background checks before conducting inspections. In addition, support that the three sampled inspectors meet the minimum insurance limits for the current effective periods.
- Status2018-FW-0003-001-DOpenClosedClosed on November 07, 2019
We recommend that the Deputy Assistant Secretary for REAC require REAC to execute administrative action related to outside standards determinations for five inspectors.
- Status2018-FW-0003-001-EOpenClosedClosed on November 14, 2019
We recommend that the Deputy Assistant Secretary for REAC require REAC to develop and implement processes and procedures, in accordance with its system security plan and the HUD Handbook, Information Technology Security Policy, to ensure that annual assessments and continuous monitoring of the security controls are performed and that security control failures are prevented and corrected when identified.
- Status2018-FW-0003-001-FOpenClosedClosed on September 04, 2019
We recommend that the Deputy Assistant Secretary for REAC require REAC to establish and implement written processes and procedures to verify the accuracy of the unit numbers sampled and entered for inspection by the inspector, which could include requiring (1) inspectors to upload a picture of the rent roll to the data collection device, (2) housing agencies to maintain a copy of the rent roll used, and (3) inspectors and public housing agencies to sign a certification stating that the units were inspected in accordance with the sample generated by the data collection device.
2018-LA-0801 | August 26, 2018
The Office of Native American Programs Section 184 Program Continues To Operate Without Adequate Oversight 3 Years After the Prior OIG Audit
Public and Indian Housing
- Status2018-LA-0801-001-COpenClosedClosed on September 25, 2020
Develop and implement internal ONAP and OLG policies and procedures for the audit resolution process, complementing HUD Handbook 2000.06, to include management oversight and review of documents prepared and submitted to evidence that corrective actions have been adequately developed and fully implemented.
- Status2018-LA-0801-001-EOpenClosedClosed on April 11, 2025
Develop and implement policies and procedures, coordinating with other program offices as needed, to track and make administrative contract expense fund expenditures readily available for review.
- Status2018-LA-0801-001-FOpenClosedClosed on August 05, 2022
Develop and implement a comprehensive plan to use unobligated administrative contract expense funds.
- Status2018-LA-0801-001-GOpenClosedClosed on May 19, 2021
Consider adding additional OLG staff, including a full time director to provide additional leadership and management oversight.
2018-LA-0004 | August 12, 2018
HUD Did Not Always Ensure That Grantees Maintained the Required Depository Agreements for Investing Program Funds
Public and Indian Housing
- Status2018-LA-0004-001-AOpenClosedClosed on August 13, 2019
Obtain the required depository agreements for two5 grantees to ensure that they invest program funds in investment securities for use in carrying out affordable housing activities in accordance with PIH Notices 2014-21, section 4, and 2015-08, section 7.
- Status2018-LA-0004-001-BOpenClosedClosed on August 13, 2019
Strengthen monitoring controls to ensure that current and future grantees maintain the required depository agreements before allowing them to invest program funds in investment securities for use toward affordable housing activities.
- Status2018-LA-0004-001-COpenClosedClosed on August 13, 2019
Update HUD’s Indian Housing Block Grant Recipient Self-Monitoring Guidebook to replace the expired requirement for investing program funds with PIH Notice 2015-08 and ensure that the Guidebook is updated with the latest requirements to ensure that grantees remain compliant with program requirements.
2018-OE-0004 | August 12, 2018
HUD IT System Management and Oversight of the Section 184 Program
Public and Indian Housing
- Status2018-OE-0004-01OpenClosedClosed on June 25, 2020
Direct PIH and OCIO to develop a comprehensive project plan, documenting the milestones and dates for addressing the gaps in ONAP-LOS capabilities (functionality and reports) and the 25 recommendations made during HUD OCIO's project health assessment
- Status2018-OE-0004-02OpenClosedClosed on June 25, 2020
Direct all stakeholders to identify all viable options to securely resolve the ONAP-LOS access issues, so authorized Section 184 lenders can access the system. The best solution should not impose unacceptable risk to business processes or sensitive data. Current program offices involved are OCIO, PIH, and FHA, while others may also be identified
- Status2018-OE-0004-03OpenClosedClosed on March 06, 2024
Direct PIH and OCIO to ensure that the Section 184 program transitions away from dependency on CHUMS.