We audited the Springfield Housing Authority’s Public Housing Operating Fund and Capital Fund programs because the Authority ranked fifth highest on our risk assessment of Massachusetts public housing agencies and is the third largest in the State. In addition, we had not audited the Authority in more than 10 years. The objective of the audit was to determine whether the Authority complied with procurement and contract administration requirements for its Public Housing Operating Fund and Capital Fund programs.

Authority officials did not always comply with Federal procurement requirements and their own procurement policy. Specifically, they did not always adequately perform and document procurement, and contract terms were not always consistent with other procurement documents. In addition, Authority officials did not always comply with contract administration requirements. Specifically, they did not always ensure that (1) contract amounts were not exceeded, (2) change orders were approved in a timely manner, and (3) completion documents were submitted as required. These conditions occurred because Authority officials did not always follow their procurement policies and were not always aware of Federal procurement requirements due to a lack of training. Further, the Authority had inadequate controls to ensure that it adequately documented the history of the procurements and did not exceed contract amounts. As a result, the Authority incurred $37,941 in ineligible costs, $916,132 in unsupported costs, and $408,968 in unspent funds that may need to be reallocated.

We recommend that the Director of the U.S. Department of Housing and Urban Development’s Boston Office of Public Housing require Authority officials to (1) repay from non-Federal funds the $37,941 in ineligible costs, (2) support that $916,132 spent on contracts was fair and reasonable or repay the funds, (3) support that $408,968 in funds not yet spent on contracts was fair and reasonable or reallocate the funds, (4) establish and implement adequate record-keeping procedures to comply with Federal procurement requirements, and (5) establish and implement adequate controls so the Authority does not exceed the contract amount without appropriate contract amendments and approvals.

 

Recommendations

Public and Indian Housing

  •  
    Status
      Open
      Closed
    2020-BO-1002-001-A
    $916,132.00
    Questioned Costs

    Recommendations with questioned costs identify costs: (A) resulting from an alleged violation of a law, regulation, contract, grant, or other document or agreement governing the use of Federal funds; (B) that are not supported by adequate documentation (also known as an unsupported cost); or (C) that appear unnecessary or unreasonable.

    Closed on November 03, 2020

    Support that $916,132 spent on contracts was fair and reasonable in accordance with Federal requirements or repay the Operating Fund or Capital Fund program from non-Federal funds any amount that cannot be supported.

  •  
    Status
      Open
      Closed
    2020-BO-1002-001-B
    $408,968.00
    Funds Put to Better Use

    Recommendations that funds be put to better use estimate funds that could be used more efficiently. For example, recommendations that funds be put to better use could result in reductions in spending, deobligation of funds, or avoidance of unnecessary spending.

    Closed on November 03, 2020

    Support that $408,968 in funds not yet spent on contracts would be fair and reasonable or reallocate the funds to ensure that they will be put to their intended use.

  •  
    Status
      Open
      Closed
    2020-BO-1002-001-C
    Closed on October 06, 2020

    Reprocure any contracts for which cost reasonableness cannot be supported and contracts were not properly awarded to ensure compliance with HUD requirements.

  •  
    Status
      Open
      Closed
    2020-BO-1002-001-D
    Closed on June 23, 2020

    Ensure that all Authority staff members working with procurements and contract administration receive Federal procurement training.

  •  
    Status
      Open
      Closed
    2020-BO-1002-001-E
    Closed on June 22, 2020

    Establish and implement adequate record-keeping procedures to comply with Federal procurement requirements, including a checklist for the file to ensure that they complete all procurement requirements and receive all required documents.

  •  
    Status
      Open
      Closed
    2020-BO-1002-001-F
    Closed on November 19, 2020

    Ensure that all architectural and engineering contracts or task orders awarded during our audit period are reviewed for cost reasonableness.

  •  
    Status
      Open
      Closed
    2020-BO-1002-002-A
    $37,941.00
    Questioned Costs

    Recommendations with questioned costs identify costs: (A) resulting from an alleged violation of a law, regulation, contract, grant, or other document or agreement governing the use of Federal funds; (B) that are not supported by adequate documentation (also known as an unsupported cost); or (C) that appear unnecessary or unreasonable.

    Closed on November 03, 2020

    Repay the Operating Fund program from non-Federal funds for the $37,941 in ineligible costs when the amount paid exceeded the contract value.

  •  
    Status
      Open
      Closed
    2020-BO-1002-002-B
    Closed on June 22, 2020

    Establish and implement adequate controls so the Authority does not exceed the contract amount without appropriate contract amendments and written approvals.

  •  
    Status
      Open
      Closed
    2020-BO-1002-002-C
    Closed on June 22, 2020

    Establish and implement adequate controls to obtain all of the required project completion documentation prior to final payment.