Closed Date:
Junio 22, 2021

Repay from non-Federal funds the $1,190,977 in ineligible costs charged to the program.

Publication Report

2018-BO-1005 | Septiembre 19, 2018

The State of Connecticut Did Not Ensure That Its Grantees Properly Administered Their Housing Rehabilitation Programs

We audited the State of Connecticut’s Small Cities Community Development Block Grant program based on an Office of Inspector General risk assessment, which ranked the State as the highest risk grantee in Connecticut.  Our audit objective was to... más

Related Recommendations

Community Planning and Development

  •  
    Status
      Open
      Closed
    2018-BO-1005-001-B
    Closed on Junio 22, 2021
    $434,970.00
    Questioned Costs

    Recommendations with questioned costs identify costs: (A] resulting from an alleged violation of a law, regulation, contract, grant, or other document or agreement governing the use of Federal funds; (B] that are not supported by adequate documentation (also known as an unsupported cost]; or (C] that appear unnecessary or unreasonable.

    Summary

    Repay from non-Federal funds the $434,970 in unreasonable costs charged to the program

  •  
    Status
      Open
      Closed
    2018-BO-1005-001-C
    Closed on Junio 22, 2021
    $249,015.00
    Questioned Costs

    Recommendations with questioned costs identify costs: (A] resulting from an alleged violation of a law, regulation, contract, grant, or other document or agreement governing the use of Federal funds; (B] that are not supported by adequate documentation (also known as an unsupported cost]; or (C] that appear unnecessary or unreasonable.

    Summary

    Support $249,015 in program costs spent on a 2014 grant for which the grantee was unable to provide a tier one environmental review record or repay from non-Federal funds any amount that cannot be supported

  •  
    Status
      Open
      Closed
    2018-BO-1005-001-D
    Closed on Junio 22, 2021
    $676,922.00
    Questioned Costs

    Recommendations with questioned costs identify costs: (A] resulting from an alleged violation of a law, regulation, contract, grant, or other document or agreement governing the use of Federal funds; (B] that are not supported by adequate documentation (also known as an unsupported cost]; or (C] that appear unnecessary or unreasonable.

    Summary

    Support $676,922 for contracts that were improperly procured or repay from non-Federal funds any amount that cannot be supported.

  •  
    Status
      Open
      Closed
    2018-BO-1005-001-E
    Closed on Junio 22, 2021
    $422,600.00
    Questioned Costs

    Recommendations with questioned costs identify costs: (A] resulting from an alleged violation of a law, regulation, contract, grant, or other document or agreement governing the use of Federal funds; (B] that are not supported by adequate documentation (also known as an unsupported cost]; or (C] that appear unnecessary or unreasonable.

    Summary

    Support $422,600 in program income that was not used before additional grant fund drawdowns or repay from non-Federal funds any amount that cannot be supported

  •  
    Status
      Open
      Closed
    2018-BO-1005-001-F
    Closed on Julio 22, 2022
    Summary

    Strengthen controls over program oversight to ensure that grantees comply with their agreements and program requirements, including tier two environmental reviews, contract procurements, and homeowner and project eligibility, to ensure that (1) all income, including rental income, is considered; (2) loan-to-value ratios do not exceed 90 percent without State approval; and (3) projects do not exceed the program limits without State approval.

  •  
    Status
      Open
      Closed
    2018-BO-1005-001-G
    Closed on Julio 22, 2022
    Summary

    Strengthen controls over monitoring to ensure that onsite monitoring and monitoring letters are completed in a timely manner and sufficient supporting documentation is required and reviewed by those responsible for grant oversight.

  •  
    Status
      Open
      Closed
    2018-BO-1005-002-A
    Closed on Agosto 06, 2020
    Summary

    Develop and implement policies and procedures to assess the validity of all program complaints to ensure that they are addressed and resolved in a timely manner.

  •  
    Status
      Open
      Closed
    2018-BO-1005-002-B
    Closed on Agosto 06, 2020
    Summary

    Provide additional guidance to its grantees regarding its policy stating that the repair or replacement of paved surfaces should be minimal in cost and incidental to the rehabilitation of the dwelling, including whether grantees are required to consult with the State before starting the work.