We recommend that HUD for its disaster-related program wide activities, require grantees to provide documentation showing that they have upfront collaboration with partnering entities in executing the grant program. If the grantee plans to hire contractors, HUD should ensure that grantees have a plan to quickly onboard contractors early in the program.

Publication Report

2025-FW-0001 | Febrero 21, 2025

Grantees Were Delayed in Completing National Disaster Resilience Program Activities, but Remain On Track to Accomplish Goals

We audited the project activity status for 12 grantees that received funds under the U.S. Department of Housing and Urban Development’s (HUD) Community Development Block Grant (CDBG) National Disaster Resilience (NDR) grant to determine whether the... más

Related Recommendations

Community Planning and Development

  •  
    Status
      Open
      Closed
    2025-FW-0001-001-A
    Summary

    We recommend that HUD work with Connecticut and Shelby County to fully realize the program benefits by (1) assessing whether any of the current project activities need to be replaced with more viable project activities, thereby ensuring that any modifications to the project activities will lessen the susceptibility of rain and flood events; (2) assessing whether administrative funds have been properly allocated and charged to identify any possible cost savings; (3) determining whether enough administrative funds or other available funds exist to complete the administration of the grant project activities; and (4) developing and implementing a written plan of action that will assist with expediting the project activities that could reasonably be expected to be completed by the September 30, 2029, deadline.

  •  
    Status
      Open
      Closed
    2025-FW-0001-001-B
    Summary

    We recommend that HUD conduct onsite or remote monitoring for the City of Minot and Tennessee, which have not had any monitoring since grant inception, to ensure that these grantees are on track to meet their program goals.

  •  
    Status
      Open
      Closed
    2025-FW-0001-001-C
    Summary

    We recommend that HUD for grantees with delayed project activities (California, Connecticut, Louisiana, Tennessee, Virginia, New York City, Minot, and Shelby County), require each grantee to provide a detailed timeline with milestone dates of when projects should be completed and provide updates to ensure that grantees stay on schedule.

  •  
    Status
      Open
      Closed
    2025-FW-0001-001-D
    Summary

    We recommend that HUD for its disaster-related program wide activities, revise the action plan and quarterly performance review checklists to a format that more specifically and directly addresses the subject program.