Develop and implement a plan to manage and reduce its backlog of work orders. This plan should include but not be limited to (1) assessing and addressing staffing needs; (2) creating a timeline for completion of the work orders to ensure that its properties are maintained in decent, safe, and sanitary condition and in good repair; and (3) providing documentation showing that it is on track to meet the completion timeframe.
Publication Report
2025-CH-1001 | Febrero 25, 2025
The Boston Housing Authority Did Not Always Comply With HUD’s and Its Own Requirements for Its Public Housing Program Units
We audited the Boston Housing Authority’s public housing program to determine whether the physical condition of the Authority’s program units complied with the U.S. Department of Housing and Urban Development’s (HUD) and the Authority’s requirements.... másRelated Recommendations
Public and Indian Housing
- Status2025-CH-1001-001-AOpenClosedSummary
Provide evidence to support that the Authority corrected the 11 unit deficiencies for the 5 units and 7 building deficiencies for 4 buildings with outstanding deficiencies.
- Status2025-CH-1001-001-BOpenClosedSummary
Determine the frequency of its quality control reviews of its inspections and work orders and update its quality control policy, training materials, and other resources as appropriate to ensure that its quality control process is consistently implemented.
- Status2025-CH-1001-001-COpenClosedSummary
Support that it has implemented its quality control policy for (1) monitoring the effectiveness of its unit and building inspections to ensure compliance with HUD’s and its own requirements and (2) reviewing work orders to ensure that cited deficiencies are corrected in accordance with HUD’s and its own requirements.
- Status2025-CH-1001-002-AOpenClosedSummary
Provide evidence to support that the Authority corrected the four non-life-threatening deficiencies for the three units with outstanding deficiencies.
- Status2025-CH-1001-002-BOpenClosedSummary
Implement adequate procedures and controls to ensure that the deficiencies identified during annual self-inspections are properly categorized and corrected in a timely manner.
- Status2025-CH-1001-002-DOpenClosedSummary
Implement adequate procedures and controls to ensure that inspection reports are uploaded to the Authority’s electronic filing system and work orders are created in a timely manner. This process should include but not be limited to providing training to its staff on the Authority’s systems, establishing timeframes for the creation of work orders, and monitoring the work order process.
- Status2025-CH-1001-003-AOpenClosedSummary
Provide evidence to support that the Authority corrected the 3 non-life-threatening health and safety, and 19 non-health and safety deficiencies.
- Status2025-CH-1001-003-BOpenClosedSummary
Develop and implement adequate procedures and controls to ensure that (1) the deficiencies identified during REAC inspections are corrected in a timely manner and (2) documentation is maintained to support that repairs were made.
- Status2025-CH-1001-003-COpenClosedSummary
Implement adequate controls to ensure that the Authority’s information system properly tracks the completion of work orders.
- Status2025-CH-1001-003-DOpenClosedSummary
Implement adequate controls to ensure that the correction of life-threatening deficiencies is reported to HUD accurately and in a timely manner.